Question
1 Approved Answer
A refurbishment project consists of the following activities:ActivityDuration ( days ) PredecessorsA 5 - B 7 A C 2 A D 3 B , C
A refurbishment project consists of the following activities:ActivityDuration daysPredecessorsA B A C A D B C E B F E What is the duration of this project?Answer Question The critical path is:Multiple choice Question ACDABEFABDABDENone of the aboveDue to a late delivery of equipment, activity C is delayed by days. How many days can activity D now be delayed without delaying the completion of the project?Answer Question