Question

1 Approved Answer

A residential project has the following information: Four major activities are scheduled across a 4 - month time span ( shown in the below bar

A residential project has the following information:
Four major activities are scheduled across a 4-month time span (shown in the below bar chart).
Assuming the monthly indirect cost (i.e., site office costs, telephone, heat, light, and supervisory salaries) is $5,000.
Assuming the direct costs are evenly distributed across the duration of the activity
first month 80,000
2nd month 120,000
3rd month 90,000
4th month 50,000
What is the total cost at month 3?
2.For the same residential project, if:
The markup is 8%
The owner retains 10% of all validated progress payment until completion
How much money the contractor is expected to receive from the owner at month 3?
3.For the same residential project, if the contractor will receive 9.6% of the contract price as advance payment, how much money the contractor is expected to received from the owner at month 3?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting Tools for business decision making

Authors: Jerry J. Weygandt, Paul D. Kimmel, Donald E. Kieso

5th edition

470506954, 471345881, 978-0470506950, 9780471345886, 978-0470477144

More Books

Students also viewed these Accounting questions