A resource buffer is placed before a critical task that uses a new resource type, and is also known as a ______ buffer. A. milestone
A resource buffer is placed before a critical task that uses a new resource type, and is also known as a ______ buffer. A. milestone B. feeding C. contention D. project
I answered B feeding buffer as it made the most sense being that it's the only resource placed before a critical task. The others didn't quite fit the puzzle piece. Can someone advise where this went wrong. Thank you.