A resource buffer is placed before a critical task that uses a new resource type, and is also known as a ______ buffer. A. milestone

A resource buffer is placed before a critical task that uses a new resource type, and is also known as a ______ buffer. A. milestone B. feeding C. contention D. project

I answered B feeding buffer as it made the most sense being that it's the only resource placed before a critical task. The others didn't quite fit the puzzle piece. Can someone advise where this went wrong. Thank you.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Strategic Management Concepts And Cases

Authors: Cathy A Enz, Jeffrey S Harrison

2nd Edition

047008359X, 9780470083598

More Books

Students also viewed these General Management questions

Question

13. Give four examples of psychological Maginot lines.

Answered: 1 week ago