Question
a) Shah Ltd needs a component for one of its products. It can subcontract production of the component to a subcontractor who will provide the
a) Shah Ltd needs a component for one of its products. It can subcontract production of the component to a subcontractor who will provide the components for $20 each. Shah Ltd can produce the components internally for total variable cost of $15 per component. Shah Ltd has spare capacity.
Required:
Should the component be subcontracted or produced internally? (2 marks)
b) Now assume that Shah Ltd has no spare capacity, so it can only produce the component internally by reducing its output of another of its products. While it is making each component, it will lose contributions of $12 from the other product.
Required:
Should the component be subcontracted or produced internally? (3 marks)
c) What factors, other than the immediately financially quantifiable, would you consider when making a make-or-buy decision? (3 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started