A shallow trench for a 1000 feet waterline installation willtake ten days. It will take four days
Fantastic news! We've Found the answer you've been seeking!
Question:
A shallow trench for a 1000 feet waterline installation willtake ten days. It will take four days to install the first 400 feetof pipe. A water meter will then be installed during the followingtwo days at the end of the pipe. After the meter is installed, theremaining 600 feet of pipe will be installed in six days. Develop alinear schedule for this project.