A short project consists of 3 tasks, which are done in series (sequentially): A -> B -> C. TASK are A, B, C EXPECTED DURATION
A short project consists of 3 tasks, which are done in series (sequentially): A -> B -> C.
TASK are A, B, C
EXPECTED DURATION
8, 12, 9 (days)
STANDARD DEVIATION
1.3, 6.6, 4.7
A 8 1.3
B 12 6.6
C 9 4.7
Determine the standard deviation of the critical path (CP). Round your result to 2 decimal places, if applicable.