Question
1 Approved Answer
A . Should be used on rare occasions, for exceptional performance B . Are the responsibility of the functional manager C . Should be included
A Should be used on rare occasions, for exceptional performance
B Are the responsibility of the functional manager
C Should be included in the projects Staffing Management Plan
D Are perquisites reserved for the project manager and project sponsor