A simple CPM network has three activities, A , B , and C . A is an immediate predecessor of B and of C .
A simple CPM network has three activities, A B and C A is an immediate predecessor of B and of is an immediate predecessor of The activity durations are
The network has no critical path.
The critical path is AC duration
The critical path is ABC duration
The critical path cannot be determined without knowing PERT expected activity times.
The critical path is duration