A simple project listing of five activities and their respective time estimates are presented here: table [ [ , Immediate, ] , [ Activity
A simple project listing of five activities and their respective time estimates are presented here:
tableImmediate,ActivityPredecessor,Time in DaysANone,BACADB and CED
Using CPM which activities make up the critical path?
Step by Step Solution