A small assembly line for the assembly of power steering pumps needs to be balanced. Below is the precedence diagram. The cycle time is given as 1.5 minutes per pump. Balancing the line using the longest-task-time-first method, which tasks would be assigned to which workstations? In other words, balance the assembly line, putting the tasks into the appropriate workstations. (like we did in class). Write out your answer in the answer box below. Such as: Workstation # 1 will have Workstation #2 will have Workstation # 3 will have You will have 3 workstations used. For this one, there is 1 point possible for the correct answer for Each Workstation. So, 3 points possible on this question Precedence Diagram. For each task (the letters in the circle), the corresponding task time is above the circle. The corresponding task times are in minutes in the diagram. 0.4 A small assembly line for the assembly of power steering pumps needs to be balanced. Below is the precedence diagram. The cycle time is given as 1.5 minutes per pump. Balancing the line using the longest-task-time-first method, which tasks would be assigned to which workstations? In other words, balance the assembly line, putting the tasks into the appropriate workstations. (like we did in class). Write out your answer in the answer box below. Such as: Workstation # 1 will have Workstation #2 will have Workstation # 3 will have You will have 3 workstations used. For this one, there is 1 point possible for the correct answer for Each Workstation. So, 3 points possible on this question Precedence Diagram. For each task (the letters in the circle), the corresponding task time is above the circle. The corresponding task times are in minutes in the diagram. 0.4