A small startup company conducts biotechnology lab tests. The tests are processed in a sequential line layout. This year the sales expected to reach testing

A small startup company conducts biotechnology lab tests. The tests are processed in a sequential line layout. This year the sales expected to reach testing 50,000 units and increase by 25% for next year. An attempt is made to improve the productivity of the process. Over time, the process tasks and activities were developed with little consideration for efficiency. (Startup)

Resource Unit Load (Ti), Seconds
A 85
B 85
C 70
D 70
E 55
F 90
G 65
H 90
I 40

What is the maximum capacity per day, assuming that it is operated for one 8-hour shift

Assuming the line operates 200 days per year and current set up and capacity, can this line meet the demand for next year?

The unit manager for Resource C and D have diligently worked to reduce the unit load from 70 seconds to 55 seconds, how did that affect the process output?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

No Nonsense Management A General Managers Primer

Authors: Richard S. Sloma

1st Edition

1893122603, 978-1893122604

More Books

Students also viewed these General Management questions