Question
A small textile plant was constructed in 2008. The major equipment, costs, and factors are shown in the table below . Equipment Reference Size Reference
A small textile plant was constructed in 2008. The major equipment, costs, and factors are shown in the table below .
Equipment | Reference Size | Reference Cost | Cost-Capacity Factor | New Design Size |
Finishing machine | 150 yd/min | $955,000 | 0.81 | 200 yd/min |
Jet dyer | 200 yd/min | $1,190,000 | 0.76 | 450 yd/min |
Steam dyer | 100 yd/min | $800,000 | 0.68 | 175 yd/min |
Estimate the cost (in dollars) to build a new plant in 2018 if the index for this type of equipment has increased at an average rate of 2 % per year for the past 10 years. (Enter your answer as a number without the dollar $ sign.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started