A software development team is using the Agile development life cycle model for a new project. During a sprint, they realize that a feature they
A software development team is using the Agile development life cycle model for a new project.
During a sprint, they realize that a feature they are working on is more complex than initially thought and cannot be completed within the current sprint.
What should the team do
answer
Break the feature down into smaller tasks and distribute them over the next few sprints.
Move on to the next feature and return to the complex feature in a future sprint.
Drop the feature from the project.
Continue working on the feature past the end of the sprint until it is completed.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started