Question
A startup firm is considering building a ski resort in a state that plans to construct a new airport to attract more tourists. The state
A startup firm is considering building a ski resort in a state that plans to construct a new airport to attract more tourists.
The state will announce in one year whether the airport plan is approved in the state budget, and the construction is expected to take three years to complete.
(we assume that once the plan is approved, the airport will be built successfully).
It takes threes years to build the hotel and the firm wants to hotel to be ready when the new airport is put into operation.
Projected Annual Cash Outflow to Build The Hotel Over 3-Years:
In 1-Year: Legal documents preparation, Build foundation $2
In 2-Years: Main construction $3
In 3-Years: Finishing $7
Projected Present Value from Operating the Hotel in Two Scenarios
Scenario #1: Good Case: The airport plan passes the state budget and the airport is built: $29.
Scenario #2: Bad Case: The airport plan fails to pass the state budget: $4.
For simplicity, lets assume that the discount rate is 0%. The consulting team predicts that the probability the airport plan passes the state budget is 0.3
The firm can pay extra money to obtain an option to terminate the project at the end of the first year in the event that the plan fails to pass the budget.
How much is this option worth?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started