A static budget a. Is considered a good choice for benchmarks in preparing a performance report. b. Is prepared for a particular level of activity.
A static budget a. Is considered a good choice for benchmarks in preparing a performance report. b. Is prepared for a particular level of activity. c. Computes expected costs for a range of activity levels. d. Compares actual costs with budgeted costs. e. None of these choices are correct.