Question
A steel product is manufactured by starting with raw material (carbon steel wire) and then processing it sequentially through five operations using machines A to
A steel product is manufactured by starting with raw material (carbon steel wire) and then processing it sequentially through five operations using machines A to E, respectively (see table below). This is the only use that the five machines are put to. The hourly rates for each machine are given in the table. Answer the following questions. Use the original output rates to answer each question (i.e., disregard any changes mentioned in previous questions) |
Operation: | 1 | 2 | 3 | 4 | 5 |
Machine: | A | B | C | D | E |
Hourly unit output rate: | 70 | 80 | 30 | 70 | 80 |
Consider the following questions. |
a. | What is the maximum output per hour of the steel product? |
Maximum output per hour | products |
b. | By how much would the output be improved if B was increased to 90? |
By | products |
c. | By how much would the output be improved if C was increased to 50? |
By | products |
d. | By how much would the output be improved if C was increased to 70? |
By | products |
e. | What is the effect on the system if machine A can only manage an output of 50 in one hour? |
We lose | products |
f. | What is the effect on the system if machine C can only manage an output of 20 in one hour? |
We lose | products |
g. | What is the effect on the system if machine B is allowed to drop to an output of 50 in one hour? |
We lose | products |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started