A student accountant is calculating the relevant cost of a new project. As part of the calculation they need to work out the value to

A student accountant is calculating the relevant cost of a new project. As part of the calculation they need to work out the value to be included for labour.

Details of the labour force needed is shown below;

Cost of labour

The company has 5 permanent employees who are on a 35 hour week contract. The employees are expected to come to work even if there is nothing to do. Currently there is spare capacity of 80 hours. If the project goes ahead each employee would be required to work 22 hours on the project.

They are paid 14 an hour with overtime being paid at time and a half.

Required

Is the cost of labour a relevant cost to the new project? Answer 1Choose...YesNo

What is the relevant cost (if any) that would be charged to the project for labour? Answer 2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

IT Auditing Using A System Perspective Premier Reference Source

Authors: Robert Elliot Davis

1st Edition

1799855481, 978-1799855484

More Books

Students also viewed these Accounting questions

Question

4.7 Identify the specific types of adjustment disorders.

Answered: 1 week ago