A supplier is late with a delivery, which has caused a delay in completion of Derek and Addison's project. In which part of their project
A supplier is late with a delivery, which has caused a delay in completion of Derek and Addison's project. In which part of their project status report would Derek and Addison discuss this? Question 33 options: Problems encountered Project overview Impact on budget The delay should not be mentioned