Question
1 Approved Answer
A supplier of electrical generators chooses to carry safety stock of 8 generators. If their demand rate is 4 per day and the lead time
A supplier of electrical generators chooses to carry safety stock of 8 generators. If their demand rate is 4 per day and the lead time is 11 days, what is the reorder point