A task has an optimistic completion time of 8 days, a most likely time of 11 days, and a pessimistic time of 14 days. The
A task has an optimistic completion time of 8 days, a most likely time of 11 days, and a pessimistic time of 14 days. The expected task duration is:
A. | 10 days | |
B. | 11 days | |
C. | 11.5 days | |
D. | 10.5 days | |
E. | 12 days | |
F. | 9.5 days |