Question
A task with hourly rate of $10.10 per hour and was baselined at 10000 hours, it is assumed that the total budget will be
A task with hourly rate of $10.10 per hour and was baselined at 10000 hours, it is assumed that the total budget will be spent equally during the project duration. Now, 4950.50 hours have been spent and it needs this same amount of time to complete. a. Calculate: PV, AC, EV, SV, CV, BAC, CPI, SPI (15 pts) b. Comment on the progress of project from point of view of: i Budgetary (5 pts) ii. Schedule (5 pts)
Step by Step Solution
3.42 Rating (158 Votes )
There are 3 Steps involved in it
Step: 1
Question Qa Earned value EV Number of hours spentNumber of hours budge...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Canadian Income Taxation Planning And Decision Making
Authors: Joan Kitunen, William Buckwold
17th Edition 2014-2015 Version
1259094332, 978-1259094330
Students also viewed these Accounting questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App