a team is feeling presuured the being development work due to tight porject deadlines. there are stakeholders with similar functions located in multple countries. to
a team is feeling presuured the being development work due to tight porject deadlines. there are stakeholders with similar functions located in multple countries. to accelerate the process the business analyst has limited te requirements elicitation sessions to times that work for stakeholders in on time zone. to reduce the rish with this approach which step should the business analyst take