A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task best defines: Group of answer choices Program

A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task best defines:
Group of answer choices
Program Evaluation Review Technique (PERT).
Computer Aided Software Engineering (CASE).
flowcharting.
Gantt.
Unified Modeling Language (UML).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Internals A Deep Dive Into How Distributed Data Systems Work

Authors: Alex Petrov

1st Edition

1492040347, 978-1492040347

More Books

Students also viewed these Databases questions

Question

6. What is process reengineering? Why is it relevant to training?

Answered: 1 week ago