A textile manufacturing company is implementing Lean principles. Requirements: Calculate the Overall Equipment Effectiveness (OEE) for a weaving machine that runs 24 hours a day,
- A textile manufacturing company is implementing Lean principles.
- Requirements:
- Calculate the Overall Equipment Effectiveness (OEE) for a weaving machine that runs 24 hours a day, 7 days a week. The machine's availability is 80%, performance efficiency is 85%, and quality rate is 90%.
- Recommend actions to improve OEE.
- Justify how improving OEE aligns with Lean manufacturing principles.