Question

1 Approved Answer

A time and materials (T&M) contract places all of the project risk on the ______. A. insurer B. contractor(s) or subcontractor(s) C. client D. attorneys

A time and materials (T&M) contract places all of the project risk on the ______.

A. insurer

B. contractor(s) or subcontractor(s)

C. client

D. attorneys who wrote the contract