A utility company lays cable for a number of utilities. The company's daily demand for cable is normally distributed with a mean of 2050 feet
A utility company lays cable for a number of utilities. The company's daily demand for cable is normally distributed with a mean of 2050 feet and a standard deviation of 363 feet. When cable is ordered from the supplier, it requires 7 days to arrive.
\begin{tabular}{|c|c|c|c|c|c|c|c|c|c|c|} \hline & & & & & & & & & & \\ \hline z & 0.00 & 0.01 & 0.02 & 0.03 & 0.04 & 0.05 & 0.06 & 0.07 & 0.08 & 0.09 \\ \hline 0.0 & .0000 & .0040 & .0080 & .0120 & .0160 & .0199 & 0239 & .0279 & .0319 & .0359 \\ \hline 0.1 & .0398 & .0438 & .0478 & .0517 & .0557 & .0596 & .0636 & .0675 & .0714 & .0753 \\ \hline 0.2 & .0793 & .0832 & .0871 & .0910 & .0948 & .0987 & .1026 & .1064 & .1103 & .1141 \\ \hline 0.3 & .1179 & .1217 & .1255 & .1293 & .1331 & .1368 & .1406 & .1443 & .1480 & .1517 \\ \hline 0.4 & .1554 & .1591 & .1628 & .1664 & .1700 & .1736 & .1772 & .1808 & .1844 & .1879 \\ \hline 0.5 & .1915 & .1950 & .1985 & .2019 & .2054 & 2088 & .2123 & .2157 & 2190 & 2224 \\ \hline 0.6 & .2257 & .2291 & .2324 & .2357 & .2389 & .2422 & 2454 & 2486 & .2518 & 2549 \\ \hline 0.7 & .2580 & .2612 & .2642 & .2673 & .2704 & .2734 & .2764 & .2794 & .2823 & 2852 \\ \hline 0.8 & .2881 & .2910 & 2939 & 2967 & 2995 & .3023 & .3051 & .3078 & .3106 & 3133 \\ \hline 0.9 & 3159 & .3186 & 3212 & 3238 & 3264 & 3289 & .3315 & 3340 & .3365 & 3389 \\ \hline 1.0 & .3413 & .3438 & .3461 & 3485 & .3508 & .3531 & .3554 & .3577 & .3599 & 3621 \\ \hline 1.1 & .3643 & .3665 & .3686 & .3708 & .3729 & .3749 & .3770 & .3790 & .3810 & .3830 \\ \hline 1.2 & .3849 & 3869 & .3888 & 3907 & .3925 & 3944 & .3962 & .3980 & 3997 & 4015 \\ \hline 1.3 & .4032 & .4049 & .4066 & .4082 & .4099 & .4115 & .4131 & .4147 & .4162 & 4177 \\ \hline 1.4 & .4192 & .4207 & .4222 & .4236 & .4251 & .4265 & .4279 & .4292 & .4306 & 4319 \\ \hline 1.5 & .4332 & .4345 & 4357 & .4370 & 4382 & .4394 & .4406 & .4418 & 4429 & .4441 \\ \hline 1.6 & .4452 & .4463 & .4474 & .4484 & .4495 & .4505 & .4515 & .4525 & .4535 & .4545 \\ \hline 1.7 & .4554 & .4564 & .4573 & .4582 & .4591 & 4599 & .4608 & .4616 & .4625 & .4633 \\ \hline 1.8 & .4641 & 4649 & 4656 & .4664 & .4671 & .4678 & .4686 & 4693 & .4699 & 4706 \\ \hline 1.9 & .4713 & .4719 & .4726 & 4732 & .4738 & .4744 & .4750 & .4756 & .4761 & 4767 \\ \hline 2.0 & .4772 & 4778 & .4783 & .4788 & .4793 & .4798 & .4803 & .4808 & .4812 & .4817 \\ \hline 2.1 & .4821 & .4826 & .4830 & .4834 & 4838 & .4842 & .4846 & .4850 & .4854 & 4857 \\ \hline 2.2 & .4861 & .4864 & .4868 & .4871 & .4875 & .4878 & .4881 & 4884 & 4887 & .4890 \\ \hline 2.3 & .4893 & .4896 & .4898 & .4901 & .4904 & .4906 & .4909 & 4911 & .4913 & 4916 \\ \hline 2.4 & .4918 & .4920 & 4922 & .4925 & .4927 & .4929 & .4931 & .4932 & .4934 & 4936 \\ \hline 2.5 & 4938 & .4940 & 4941 & .4943 & .4945 & .4946 & 4948 & .4949 & .4951 & .4952 \\ \hline 2.6 & .4953 & .4955 & .4956 & .4957 & .4959 & .4960 & 4961 & .4962 & 4963 & 4964 \\ \hline 2.7 & .4965 & .4966 & 4967 & .4968 & 4969 & .4970 & 4971 & 4972 & 4973 & .4974 \\ \hline 2.8 & 4974 & .4975 & .4976 & .4977 & .4977 & .4978 & 4979 & 4979 & 4980 & .4981 \\ \hline 2.9 & .4981 & 4982 & 4982 & .4983 & 4984 & .4984 & .4985 & .4985 & 4986 & 4986 \\ \hline 3.0 & .49865 & .49869 & 49874 & .49878 & 49882 & .49886 & .49889 & 49893 & 49897 & 49900 \\ \hline \end{tabular} Ans. choices are given and a picture of a z table with normal value curves is given.
1. What is the reorder point if the company wants to limit the probability of a stockout to 11 percent?
a. 14,073ft b. 15,531ft c. 15,848ft d. 14,642ft e. 13,997ft
2. What is the approximate service level if the company reorders when the cable inventory reaches 15,800 feet?
a. 93.45% b. 86.71% c. 85.22% d. 88.78% e. 92.60%
3. What is the reorder point if the company only wants to provide a 13% service level?
a. 13,265ft b. 18,044ft c. 13,970 ft d. 15,411 ft e. 14,039ft
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started