Question
A work center consists of 2 machines working 8 hours a day and 5 days a week. Historically, utilization has been 75% and the efficiency
A work center consists of 2 machines working 8 hours a day and 5 days a week. Historically, utilization has been 75% and the efficiency 110%. The effective capacity, to the nearest hour, would be:
Select one:
a. 46 hours
b. 56 hours
c. 66 hours
d. 76 hours
e. None of them
A company wants to develop a level production plan for a family of products. The opening inventory is 200 units, and an increase to 800 units is expected by the end of the plan. The demand for each of the months is given in (Jan., 1200), (Feb., 1400), (Mar., 1300), (Apr., 1100), (May, 1200), (June, 1300). What will be the ending inventory in Feb.?
Select one:
a. 100
b. 200
c. 300
d. 400
e. None of thm
Given the following data, (Week, Forecast): (1, 20), (2, 30), (3, 50), and (4, 20). There are 40 on hand. The lot size is 60. The MPS has been determined as needed. Then the projected available balance at week 2 should be:
Select one:
a. 20
b. 30
c. 40
d. 50
e. None of them
If the opening inventory is 100 units, the sales are 500 units and the ending inventory is 200 units then manufacturing must produce:
Select one:
a. 200 units
b. 300 units
c. 400 units
d. 500 units
e. None of them
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started