Question

1 Approved Answer

a) You make widgets. Widgets are made up of 10 parts: 2 of Part A, 5 of Part B, and 3 of Part C. The

a) You make widgets. Widgets are made up of 10 parts: 2 of Part A, 5 of Part B, and 3 of Part C. The leadtime for combining all the parts to produce a widget is 3 weeks. The leadtime to order Part A from an outside supplier is 2 weeks. The leadtime to assemble Part B in-house is 1 week. The leadtime to produce Part C in-house is 4 weeks. You currently have no inventory of finished widgets and no inventory of Part A, Part B, or Part C. If your first demand for widgets is in week 9, in what week do you need to start making ("planned order release") Part C?

b) As above, widgets are made of Part A, Part B, and Part C. Additionally, Part B is assembled from Part D and Part A. Part D is made up of Part Q and Part P. Given that the lower-level code for the Widget is 0, what is the LLC for Part Q?

C) Using the above information, what is the low-level code (LLC) for Part A?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Multinational Management

Authors: John B. Cullen

6th edition

1285094946, 1285094948, 9781285696744 , 978-1285094946

More Books

Students also viewed these General Management questions