Question

1 Approved Answer

Abbott Manufacturing produces plastic cases for solar 'photovoltaic panels and has decided to combine orders from customers to increase work order size, and thereby, make

Abbott Manufacturing produces plastic cases for solar 'photovoltaic panels and has decided to combine orders from customers to increase work order size, and thereby, make one large production run per model type. Plastic injection molding machines are used to make these parts, and it is time consuming to clean and re-setup the machines between production runs. Each molding machine and operator works one 9-hour shift with a one-hour lunch break and one-half hour for operator breaks.
\table[[,,Setup,],[,,(Changeover),Processing],[Time per,Time per,,],[Consolidated,Work Order,Work Order,Panel],[Work Orders,Quantity,(minutes),(seconds)],[Model XVT-5 Case,8,500 panels,88,2.50],[Model UYT-3 Case,8,400,84,1.84],[Model KLY-6 Case,12,600,150,4.81]]
What is the total workload (demand) in hours for this work order mix? Round your answer to one decimal place.
The total workload is hours.
How many machines will it take to do this work in one, two, or three days? Round your answers up to the nearest whole number.
To do this work in 1 day they need machine(s).
To do this work in 2 days they need
machine(s).
To do this work in 3 days they need
machine(s).
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: R. Dan Reid, Nada R. Sanders

4th edition

9780470556702, 470325046, 470556706, 978-0470325049

More Books

Students also viewed these General Management questions

Question

=+Adapt the three-step writing process to reports and proposals

Answered: 1 week ago