Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

ABC co. has the following data: Standard batch level material costs of Rs. 12,000 for a batch of 100 units. Static budget was for 180

ABC co. has the following data: Standard batch level material costs of Rs. 12,000 for a batch of 100 units. Static budget was for 180 units. Actual was Rs. 11,000 for a production of 80 units. Calculate the static budget or planning variance. (Note: this is a batch level cost)

Rs. 1,000 (unfavourable)

Rs. 12,000 (Favourbale)

Rs. 11,000 (Favourable)

Rs. 1,000 (favourable)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Risk-Based Internal Audit

Authors: Jason Lee Mefford

1st Edition

1631922629, 9781631922626

More Books

Students also viewed these Accounting questions