Question
1 Approved Answer
ABC CO. is evaluating a new project with an estimated cost of OMR 70,000. Operating cash inflows for four years are, OMR 15,000, OMR 30,000,
ABC CO. is evaluating a new project with an estimated cost of OMR 70,000. Operating cash inflows for four years are, OMR 15,000, OMR 30,000, OMR 40,000 and OMR 15,000 respectively. The residual value at the end of the project life is OMR 20,000. The risk free discount rate is 11% and risk premium is 5%.
1. Calculate project NPV at the risk free discount rate.
a) OMR 7,000
b) OMR 20,810
c) OMR 20,180
d) OMR 7,00
2. Calculate project NPV at risk-adjusted discount rate.
a) OMR 10,180
b) OMR 860
c) OMR 10,810
d) OMR 860
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started