Question

1 Approved Answer

ABC CO. is evaluating a new project with an estimated cost of OMR 70,000. Operating cash inflows for four years are, OMR 15,000, OMR 30,000,

ABC CO. is evaluating a new project with an estimated cost of OMR 70,000. Operating cash inflows for four years are, OMR 15,000, OMR 30,000, OMR 40,000 and OMR 15,000 respectively. The residual value at the end of the project life is OMR 20,000. The risk free discount rate is 11% and risk premium is 5%.

1. Calculate project NPV at the risk free discount rate.

a) OMR 7,000

b) OMR 20,810

c) OMR 20,180

d) OMR 7,00

2. Calculate project NPV at risk-adjusted discount rate.

a) OMR 10,180

b) OMR 860

c) OMR 10,810

d) OMR 860

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

P7 Advanced Audit And Assurance Q And A 2013

Authors: ACCA Simplified

1st Edition

1492716626, 978-1492716624

More Books

Students also viewed these Accounting questions

Question

2. How should this be dealt with by the organisation?

Answered: 1 week ago

Question

explain what is meant by the term fair dismissal

Answered: 1 week ago