Answered step by step
Verified Expert Solution
Link Copied!

Question

...
1 Approved Answer

ABC Company currently produces a single product the Widget. The company is considering producing a second product called the Fidget. ABC Company has already paid

ABC Company currently produces a single product the Widget. The company is considering producing a second product called the Fidget. ABC Company has already paid a consulting firm $50,000 to identify two possible project scenarios available to ABC Company in order to get into the Fidget business. Assume that ABC Company can sell all of the Widgets and Fidgets it produces at current market prices, and that Widgets and Fidgets sell for the same price.

Project #1 is the construction of a new factory to exclusively produce Fidgets. This new factory would be located on a piece of land that ABC Company currently owns and was planning to sell for $900,000.

Project #2 is a partial renovation of the existing Widget factory in order to create a new production line to produce fidgets. The renovation would mean a decline in the ability of the company to produce as many Widgets as it has in the part, but overall, production capabilities would increase.

The initial cost of both Project #1 and Project #2 are approximately the same. The weighted average cost of capital (WACC) for ABC Company is 8%. However, the company makes an adjustment to the WACC for the purpose of computing NPV Based upon the perceived risk of the project. Information regarding the two projects is presented below:

Measure

Project #1

Project #2

IRR

11%

8%

NPV

$140,000

$175,000

Payback Period

6.4 years

6.8 years

Risk Level

High

Low

  1. If the projects are mutually exclusive, which project(s) should the company select, and why is that the correct decision?
    1. Accept both projects, because the NPV of both projects is positive.
    2. Project #2 because it has the highest NPV.
    3. Project #1 because it has the highest IRR and shortest payback period.
    4. Project #2 because it has the lowest risk and lowest IRR.

  1. If the projects are independent, which project(s) should the company select and, which is that the correct decision?
    1. Accept both projects, because the IRR of both projects meets or exceeds the WACC.
    2. Accept both projects, because the NPV of both projects is positive.
    3. Project #2 because it has the highest NPV.
    4. Project #2 because it has the highest IRR.

  1. If ABC company had paid $125,000 to the consulting firm, would this have an impact on the NPV of the project and why?
    1. It would have no effect on the NPV of the projects, because the consulting fees do not reflect an incremental cash flow.
    2. It would have no effect on the NPV of the projects, because the higher consulting fees would be offset by better future performance.
    3. It would increase the NPV of both projects because the consultants would have identified better solutions.
    4. It would decrease the NPV of both projects because of the higher cost.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Engineering Economy

Authors: William G. Sullivan, Elin M. Wicks, C. Patrick Koelling

15th edition

978-0132554909

Students also viewed these Finance questions