ABC Construction has developed the following set of activities for its budgeting process. Activity Predecessor Normal Activity Time (Days) Resulting Activity Time if Activity is
ABC Construction has developed the following set of activities for its budgeting process.
Activity | Predecessor | Normal Activity Time (Days) | Resulting Activity Time if Activity is Crashed (Days) | Total Cost to complete activity in Normal Time | Total Cost to complete activity in Crash Time |
A | -- | 4 | 2 | $200 | $600 |
B | A | 6 | 3 | $300 | $1200 |
C | A | 4 | 1 | $300 | $900 |
D | B, C | 3 | 2 | $500 | $550 |
E | D | 4 | 1 | $500 | $1700 |
Modify the problem as follows. There is now an indirect cost of $75 per day, which is in addition to the cost identified above. There is also a penalty cost of $200 per day for any project completion time over 11 days. What is the minimum cost schedule for the project and what is the total cost for this schedule? Identify what are the time and the path of this minimum cost schedule.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started