Question

1 Approved Answer

ABC construction has the following contract: Contract price $1,000,000 cost incurred cost to complete Dec 31, 2017 200,000 600,000 Dec 31, 2018 350,000 250,000 Dec

ABC construction has the following contract:

Contract price $1,000,000

cost incurred cost to complete

Dec 31, 2017 200,000 600,000

Dec 31, 2018 350,000 250,000

Dec 31, 2019 300,000 ------

850,000

Billings cash received

Dec 31, 2017 250,000 200,000

Dec 31, 2018 400,000 350,000

Dec 31, 2019 350,000 450,000

A. Prepare % of completion schedule for the three(3) years.

B. Prepare journal entries for three(3) years.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

College Accounting A Practical Approach

Authors: Jeffrey Slater, Brian Zwicker

12th Canadian edition

133133230, 978-0133133233

More Books

Students also viewed these Accounting questions