ABC construction has the following contract: Contract price $1,000,000 cost incurred cost to complete Dec 31, 2017 200,000 600,000 Dec 31, 2018 350,000 250,000 Dec
ABC construction has the following contract:
Contract price $1,000,000
cost incurred cost to complete
Dec 31, 2017 200,000 600,000
Dec 31, 2018 350,000 250,000
Dec 31, 2019 300,000 ------
850,000
Billings cash received
Dec 31, 2017 250,000 200,000
Dec 31, 2018 400,000 350,000
Dec 31, 2019 350,000 450,000
A. Prepare % of completion schedule for the three(3) years.
B. Prepare journal entries for three(3) years.