ABC Manufacturing has the following Aggregate Plan demand requirements and other data for the next four quarters. Quarter Demand Production from the previous quarter 1,500

ABC Manufacturing has the following Aggregate Plan demand requirements and other data for the next four quarters. Quarter Demand Production from the previous quarter 1,500 units 1 1,300 Beginning inventory 200 units 2 1,400 Stock out cost $50 per unit 3 1,500 Inventory holding cost $10 per unit at the end of the quarter 4 1,300 Hiring workers $4 per unit Dismissing workers $8 per unit Unit cost $30 per unit Overtime $10 extra per unit.

Using the aggregate planning Excel sheet, answer the following:  

Plan A - Pursue demand by hiring and firing. What is the total cost of the plan? 

Plan B: Mixed strategy that produces at a constant rate of 1200 and earns the rest overtime. What is the cost of this plan? 

c. Based on cost, which plan should you choose?


 

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting Tools for business decision making

Authors: Jerry J. Weygandt, Paul D. Kimmel, Donald E. Kieso

5th edition

470506954, 471345881, 978-0470506950, 9780471345886, 978-0470477144

More Books

Students also viewed these General Management questions