ABC Manufacturing uses standard costing. The standard cost for direct materials is $5 per unit, and the standard quantity is 2 units per finished product.

ABC Manufacturing uses standard costing. The standard cost for direct materials is $5 per unit, and the standard quantity is 2 units per finished product. The standard cost for direct labor is $10 per hour, and the standard labor hours are 0.5 hours per finished product. Actual data shows that 1,000 units were produced, 2,200 units of direct materials were used at $4.75 per unit, and 550 hours of direct labor were used at $9.50 per hour.

Tasks:

  1. Calculate the direct materials price variance.
  2. Calculate the direct materials quantity variance.
  3. Calculate the direct labor rate variance.
  4. Calculate the direct labor efficiency variance.


###question_divider###

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting

Authors: William K. Carter

14th edition

759338094, 978-0759338098

More Books

Students also viewed these Accounting questions

Question

Explain the concept of shear force and bending moment in beams.

Answered: 1 week ago