ABC Pvt. Ltd. is into production of motorbikes. The production plant runs 2 shifts of 9 hours each on all work days. There are 3
ABC Pvt. Ltd. is into production of motorbikes. The production plant runs 2 shifts of 9 hours each on all work days. There are 3 breaks given in each shift. 2 tea breaks of 10 minutes each and 1 lunch break of 30 minutes. There are 26 work days each month. The company fulfils the demand for 15,000 units every month. Calculate the TAKT time. SELECT THE CORRECT ANSWER 0.66 minutes 1.66 seconds 1.66 minutes