Answered step by step
Verified Expert Solution
Question
1 Approved Answer
able11.9Normal and Crash Data for General Foundry, Inc. TIME (WEEKS) COST ($) ACTIVITY NORMAL CRASH NORMAL CRASH CRASH COST PER WEEK($) CRITICAL PATH A 2
able11.9Normal and Crash Data for General Foundry, Inc.
TIME (WEEKS) COST ($)
ACTIVITY NORMAL CRASH NORMAL CRASH CRASH COST PER WEEK($) CRITICAL PATH
A 2 1 22,000 23,000 1,000 YES
B 3 1 30,000 34,000 2,000 NO
C 2 1 26,000 27,000 1,000 YES
D 4 3 48,000 49,000 1,000 NO
E 4 2 56,000 58,000 1,000 YES
F 3 2 30,000 30,500 500 NO
G 5 2 80,000 86,000 2,000 YES
H 2 1 16,000 19,000 3,000 YES
General Foundry's project crashing data are shown inTable11.9. Crash this project to 13 weeks using CPM. What is the final time for each activity after crashing?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started