According to the Salience Model of organizing Stakeholders, a stakeholder who possesses high level of power over the project team and a high level of
According to the Salience Model of organizing Stakeholders, a stakeholder who possesses high level of power over the project team and a high level of urgency but low level of legitimacy is known has ___________ stakeholder. Demanding Dominant Definitive Dangerous