ACCOUNTING PROBLEM. Exeter has a material standard of 1 pound per unit of output. Each pound has a standard price of $26 per pound. During
ACCOUNTING PROBLEM.
Exeter has a material standard of 1 pound per unit of output. Each pound has a standard price of $26 per pound. During July, Exeter paid $133,000 for 5,010 pounds, which they used to produce 4,780 units. What is the direct materials quantity variance? |
A. $5,980 unfavorable
B. $8,580 unfavorable
C. $1,840 favorable
D. $2,740 unfavorable