Acme is planning construction of a new loading ramp for its single iron mill. The initial cost of the investment is $1 million. Efficiencies from
Acme is planning construction of a new loading ramp for its single iron mill. The initial cost of the investment is $1 million. Efficiencies from the new ramp are expected to reduce costs by $100,000 for the life of the plant which is currently estimated at another 30 years. WACC = 6.94%
When will this project break-even on a discounted cash basis?