Question
Acme now wants to take into account its ability to abandon the project at the end of year 2 if the project ends up generating
Acme now wants to take into account its ability to abandon the project at the end of year 2 if the project ends up generating the worst-case scenario cash flows. If it decides to abandon the project at the end of year 2, the company will receive a one-time net cash inflow of $4,500 (at the end of year 2). The $4,500 the company receives at the end of year 2 is the difference between the cash the company receives from selling off the projects assets and the companys $3,000 cash outflow from operations. Additionally, if it abandons the project, the company will have no cash flows in years 3 and 4 of the project.
Using the information in the preceding problem, find the expected NPV of this project when taking the abandonment option into account.
$32,061
$25,091
$29,273
$27,879
What is the value of the option to abandon the project?
$2,505
$2,756
$1,754
$2,004
$2,255
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started