Question

1 Approved Answer

activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time ( all in days ) for a new contract

activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table:
\table[[,Time (days),Immediate,,Time (days),Immediate],[Activity,a,m,b,Predecessor(s),Activity,a,m,b,Predecessor(s)],[A,3,7,9,-,G,6,10,15,A, E],[B,3,4,5,-,H,10,11,12,F],[C,2,3,4,-,I,5,7,9,G],[D,7,8,9,C,J,15,17,19,C],[E,2,4,6,B, D,K,4,8,12,H, I],[F,2,3,4,A, E,,,,,]]
This exercise contains only parts b,c, and d.
b) Activities on the critical path for the project are
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Spreadsheet Modeling And Decision Analysis A Practical Introduction To Business Analytics

Authors: Cliff T. Ragsdale

8th Edition

130594741X, 978-1337517317, 1337517313, 978-1305947412

More Books

Students also viewed these General Management questions

Question

Plato concept of justice ?

Answered: 1 week ago

Question

Plato Theory of Education?

Answered: 1 week ago