Activities' estimated duration and the time intervals at which the actual progress is analyzed against the planned progress are 2 independent events in a project
Activities' estimated duration and the time intervals at which the actual progress is analyzed against the planned progress are 2 independent events in a project with latter having no relation with the former.
1.True 2. False