ACTIVITIES FOR A CONSTRUCTION PROJECT Activities Precedent activity Estimated Time Estimated Cost (weeks) (US$) A 4 10,000 B A 6,000 C A 2 4,000 D

image text in transcribed
ACTIVITIES FOR A CONSTRUCTION PROJECT Activities Precedent activity Estimated Time Estimated Cost (weeks) (US$) A 4 10,000 B A 6,000 C A 2 4,000 D B 14,000 E B, C 9,000 F C 7,000 G E, F 13,000 H D, E 4 11,000 H, G 6 20,000 a) Draw a Gantt chart from the above information b) Name all the paths available in the Gantt chart c ) Name the Critical path in the Gantt chart d) What is estimated to be the maximum cost of the project? e) Give two merits and demerits of using a Gantt chart

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Sell

Authors: Thomas N Ingram ,Raymond W Laforge ,Ramon A Avila ,Charles H Schwepker ,Michael R Williams

6th Edition

133740800X, 978-1337408004

More Books

Students also viewed these General Management questions

Question

4. What did you learn from this role-play?

Answered: 1 week ago