Question

1 Approved Answer

Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12,9, and 10, then

Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12,9, and 10, then the earliest start time for W