Answered step by step
Verified Expert Solution
Question
1 Approved Answer
activities. Time (weeks) Cost ($1,000s) Activity Description Immediate Predecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8
activities.
Time (weeks) | Cost ($1,000s) | |||||
---|---|---|---|---|---|---|
Activity | Description | Immediate Predecessor | Normal | Crash | Normal | Crash |
A | Plan needs | 10 | 8 | 30 | 70 | |
B | Order equipment | A | 8 | 6 | 120 | 150 |
C | Install equipment | B | 10 | 7 | 100 | 160 |
D | Set up training lab | A | 7 | 6 | 40 | 50 |
E | Conduct training course | D | 10 | 8 | 50 | 75 |
F | Test system | C, E | 3 | 3 | 60 |
(b)
Develop an activity schedule.
Activity | Earliest Start | Latest Start | Earliest Finish | Latest Finish | Slack |
---|---|---|---|---|---|
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F |
(c)
What are the critical activities? (Enter your answers as a comma-separated list.)
F,A,E,G,H,I
What is the expected project completion time (in weeks)?
weeks
(d)
Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes cost?
(A, B, C, D, E) =
1.34
(e)
Develop an activity schedule for the crashed project.
Activity | Earliest Start | Latest Start | Earliest Finish | Latest Finish | Slack |
---|---|---|---|---|---|
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F |
(f)
What added project cost (in thousands of dollars) is required to meet the six-month completion time?
thousands of dollars
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started