Activity 7 is directly preceded by two activities activity 5 and activity 6 . Activity 5 has an expected duration of five and an ES
Activity is directly preceded by two activitiesactivity and activity Activity has an expected duration of five and an ES time of six. Activity has an expected duration of seven and an ES time of seven. Activity has an expected duration of The ES for activity is:
Select one:
a
b
c
d
e