Activity 7 must be complete at least 1 day before Activity 8 is completedis which type of restriction? Finish to Start Start to Start Finish

"Activity 7 must be complete at least 1 day before Activity 8 is completed"is which type of restriction?
Finish to Start
Start to Start
Finish to Finsh
Start to Finish
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: Jay Heizer, Barry Render

11th edition

9780132921145, 132921146, 978-0133408010

More Books

Students also viewed these General Management questions