Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7. Activity 5-7 has an expected time of five and an ES time of
Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7. Activity 5-7 has an expected time of five and an ES time of six. Activity 6-7 has an expected time of seven and an ES